Posted April 15, 2024On Tuesday, April 16, 4 CleanUp, the street-paving contractor, will do milling, concrete work, and paving on various Bayonne streets. This work schedule is a revised version of the plans that were announced last week.
The company will mill the existing surface on seven streets to prepare them for paving. Those streets are 19th Street from Kennedy Boulevard to Avenue C; 20th Street from Avenue C to Broadway; 21st Street from Kennedy Boulevard to Avenue C; 25th Street from Broadway to Avenue E; 36th Street from Avenue C to Broadway; 44th Street from Avenue C to Broadway; and 49th Street from Avenue C to Broadway.
4 CleanUp will do concrete work on Humphreys Avenue at 5th Street.
The contractor will do paving at 5th Street from Cottage Street to Broadway, and on Cottage Street from Hobart Avenue to 5th Street.
“No Parking” signs will be posted as needed on the affected streets.