Revised Schedule For Street Work Around McDonald's By 25th Street and Broadway
Posted December 21, 2021Due to difficulties experienced by the contractor, the previously approved work schedule has changed. Parking Lot #5 resurfacing is complete. Closures for the remaining site work at the McDonalds reconstruction is as follows-
Wednesday, Dec. 23 - 25th Street will be closed at Avenue C. This will allow the contractor to support the paving of the parking lot of the restaurant itself.
Thursday, Dec. 24- The closure of Broadway, both directions, and 25th Street is authorized for the milling and paving of the City streets.
All work will occur between 7 am and 5 pm.