Revised Schedule For Street Work Around McDonald's By 25th Street and Broadway

Posted December 21, 2021

Due to difficulties experienced by the contractor, the previously approved work schedule has changed. Parking Lot #5 resurfacing is complete. Closures for the remaining site work at the McDonalds reconstruction is as follows-

Wednesday, Dec. 23 - 25th Street will be closed at Avenue C. This will allow the contractor to support the paving of the parking lot of the restaurant itself. 
 
Thursday, Dec. 24- The closure of Broadway, both directions, and 25th Street is authorized for the milling and paving of the City streets. 
 
All work will occur between 7 am and 5 pm.

Elected Officials

Meetings

  • Upcoming Meetings
  • Archived Meetings

Contact Us

City of Bayonne, NJ
630 Avenue C
Bayonne, NJ, 07002

Tel: View Directory


© City of Bayonne, NJ. All Rights Reserved. Developed by AlphaDog Solutions.
If you have any trouble with accessing information contained within this website, please contact the Clerk’s Office.
Translate Website

Translate Website